29 March 2022
Students have been enjoying seeing the form of the new building develop over this term. Now that the structural steel is all in place there are some momentous milestones planned, including:
Completing the first-floor frame
Installing windows and doors
Laying the roof sheeting
With slight delays due to COVID and wet weather, the desire is for the students to be moved into the building by Term 4, 2022.